Award of lot 7 Levensauer Hochbrücke Kiel

Award of lot 7 Levensauer Hochbrücke Kiel

On 21.02.2024, the letter of award was received with the commissioning of lot 7 as a further piece of the mosaic for the overall project to replace the Levensau High Bridge.


The North Sea-Baltic Sea Canal New Waterway Construction Office has also placed its trust in BeMo for the 5th lot and has commissioned us to build the north and south bridge abutments, including deep foundations to support the bridge aprons and the adjacent road and rail areas. The total construction period of 13 months includes a 2-month full closure of the non-electrified DB line as well as the installation of various temporary bridges to maintain pedestrian/cyclist, road and rail traffic.


We wish ourselves and all those involved in the project accident-free construction work, every success in meeting the deadlines and good cooperation.