21/01/2020

Volmarstein bridge

The last two sections of the Volmarstein bridge have been concreted.

The last two sections of the Volmarstein bridge have been concreted. The shell of the first new bridge superstructure with a total length of 285 m is now complete.
Further work will now follow, such as bridge sealing, road construction and various finishing trades.
Following the transfer of motorway traffic to this new bridge section and demolition of the old bridge structure in the direction of Cologne, work on the second bridge superstructure will then begin in autumn.