Redevelopment new Schluechterner Tunnel
Client
DB AG
Contractor
BeMo Tunnelling GmbH
In joint venture
50% in JV „Neuer Schlüchtener Tunnel“ (BeMo – Baugruppe Berlin)
Project location
Schlüchtern, Germany
Start of construction
2014
End of construction
2014
Project total value
11.4 million €
Technical Data
Production edge beam incl. grounding (construction period 18 days) in continuous operation
• Angle supporting element: 7,800 m
• Concrete edge beam: 5,500 m3
• Cable conduit DN 110: 56,000 m
• Emergency drainage DN 80: 7,800 m
• Installation control grounding switch and “Prelleiter” (earthing system) each above 7,600 m of length
Decommission existing FF system Getrac (2 tracks) and installation FF system Getrac (1 track) incl. trafficability
Installation of dry powder extinguishers, installation handrail and escape route signs.
Further project related information
Decommissions of the construction areas and infrastructure of the entire construction project “Neuer Schlüchtener Tunnel”